Airffic Inspection无人机巡检未来指南

CASE C03 · CZ · 2024

VZU Plzeň:使用带保护笼的无人机检查 700 m 长的水电站压力钢管

2024年,捷克试验机构 VZU Plzeň 用带保护笼的无人机检查了一条 700 m 长的水电压力钢管。据称省去脚手架台车后,作业从12天缩短到2天。数字来自制造商案例研究,电站未具名。

业主Hydropower plant operator (not named)
服务商VZU Plzeň (research and testing institute)
地点Czech Republic
机型Flyability Elios 3
传感器4K video, LiDAR

引入前

在现场定制搭建的脚手架台车(组装 5–6 天,拆除 5 天,另加检查时间),且有卡住的风险。

引入无人机后

一架耐碰撞无人机飞越压力钢管,采集 4K 视频和 LiDAR 点云。

成果

指标数值依据
total inspection timefrom 12 days to 2 days (stated as 80–84%)报告值
competing bidsfour other companies had attempted the job without achieving the required result报告值
注意事项与局限
  • Manufacturer/reseller case study (Flyability via COPTRZ); not independently verified.
  • The plant owner and site are not named; percentage reduction is stated inconsistently (80% vs 84%).
  • No drone limitations are described.