CASE C21 · JP · 2025

MLIT Kinki Regional Bureau: cost and schedule comparison for bridge inspection with a 360° obstacle-sensing drone

MLIT's Kinki bureau compared cost and schedule for bridge inspection with a 360° obstacle-sensing drone against inspection vehicles on three bridges. Estimated schedules shrank by roughly 40–70%, but cost savings were only about 10–20%. Flights stop in wind or rain, and hammer-sounding is still needed where falling debris could harm the public.

OwnerMLIT Kinki Regional Development Bureau
Provider—
LocationKinki region, Japan (Aji Viaduct 750 m, Yamatogawa Bridge 250.5 m, Yamatogawa-kita Viaduct 510.5 m)
AircraftSkydio drone with 360° obstacle sensing (model not stated)
SensorsRGB camera (cracks down to 0.1 mm)

Before

Close visual inspection from an under-bridge inspection vehicle.

With drones

A drone able to fly without GNSS under the deck photographs girders, piers, slabs and bearings; contractor quotes were compared with the conventional method.

Outcomes

MetricValueBasis
cost (Aji Viaduct)¥4.53M → ¥4.115M (about 10% lower); 13 → 8 daysEstimate
cost (Yamatogawa Bridge)¥3.72M → ¥3.101M (about 20% lower); 10 → 4 daysEstimate
cost (Yamatogawa-kita Viaduct)¥8.55M → ¥6.932M (about 20% lower); 25 → 8 daysEstimate
Caveats & limits
  • Figures are contractor estimates (July 2025 quotes), not measured results.
  • Cost savings are modest (about 10–20%) even though days fall sharply.
  • Flights are impossible in strong wind or rain, so schedules need slack; hammer-sounding is still required where defects could affect third parties.