Airffic InspectionThe future guide to drone inspection

CASE C13 · US ·

Dominion Energy: drone inspection of condensers at Surry nuclear power station during outages

Dominion Energy's in-house team inspects the condensers at Surry nuclear station by drone. Avoiding full scaffolding reportedly cut inspection from over a week to two 12-hour shifts and saved over $200,000 per outage. The savings figure is inconsistent within the article, and scaffolding is still needed where repairs are made.

OwnerDominion Energy
Provider—
LocationSurry County, Virginia, United States
AircraftFlyability Elios 3 (with UT payload)
Sensors4K camera, ultrasonic thickness (UT), LiDAR

Before

Scaffolding inside and around the condenser plus confined-space entry: 12–14 twelve-hour shifts to erect and 4–6 to dismantle, at least six scaffolders per shift, over $1,000/hour.

With drones

Dominion's in-house unmanned systems group flies the drone for video, UT and LiDAR; scaffolding is erected only where repairs are needed.

Outcomes

MetricValueBasis
inspection durationfrom over a week to two 12-hour shifts (headline: 8 days to 8 hours)Reported
cost per outageover US$200,000 saved (headline says US$150,000)Reported
labour12–14 scaffolders released for other workReported
Caveats & limits
  • Manufacturer case study; savings figures are inconsistent between headline and body.
  • Inspection year not stated.
  • Scaffolding is still needed for repair locations; the drone replaces only the survey step.
  • The '$3 million per day' outage figure on the page is a general industry number, not Surry-specific.

Sources

Sources checked: 2026-10-22