CASE C05 · NO ·

Returkraft: scaffold-free ultrasonic thickness inspection of a waste-to-energy boiler

Norwegian waste-to-energy plant Returkraft used a UT-equipped drone to measure boiler tube thickness. The manufacturer reports UT work falling from up to 300 hours to about 8 and the outage shortening by about 48 hours with no scaffolding. Probe angling on narrow curved tubes was difficult and pre-cleaning was required.

OwnerReturkraft (waste-to-energy plant)
Provider—
LocationKristiansand, Norway
AircraftFlyability Elios 3 with UT payload
Sensorsultrasonic thickness (UT) probe, 4K video, LiDAR

Before

10–15 scaffolders spent about 1,700 hours erecting scaffolding inside the boiler, then NDT inspectors spent about 300 hours on UT readings.

With drones

The plant's own team flew a drone with a UT probe to take tube-wall thickness readings without entering the boiler.

Outcomes

MetricValueBasis
UT inspection timeabout 8 hours (incl. battery changes) vs up to 300 hoursReported
measurementsover 150 UT readings in 2.5 hours of flightReported
outage lengthabout 48 hours shorter; 7 days of scaffolding avoidedReported
cost€450,000 stated as savedReported
Caveats & limits
  • Manufacturer case study (Flyability); the €450,000 figure is presented both as the saving and as the cost of the traditional method, so it is internally inconsistent.
  • Curved narrow tubes (44.5 mm and 57 mm) required careful probe angling; the boiler cleaning system must run first and fouling may need removing.
  • An earlier FPV drone could not fly the space and gave only visual data.
  • Year not stated in the article; city (Kristiansand) is from the plant's public identity, not the article.