ASSET / DAM
Dam inspection: one record for a tall wall, deep water and dark galleries
A downstream face that can exceed a hundred metres, an upstream face under water, inspection galleries inside the body, gates and spillways. A single dam combines height, underwater, darkness and confined space. This guide sorts out which parts of inspection built on rope access and diving can be handed to drones.
On this page
Where dams start to deteriorate
Dams are broadly concrete gravity or arch dams and embankment (fill) dams built of earth or rock. Concrete dams need watching for cracks, leakage at joints, efflorescence and surface deterioration (freeze–thaw in cold regions); fill dams for settlement, changes in seepage, and displaced riprap. In both, deterioration of gates and spillways — the equipment that releases water — bears directly on safety when it matters most.
| Element | Typical defects | If missed |
|---|---|---|
| Downstream face (concrete) | Cracks, joint leakage, efflorescence, surface spalling | Progressive deterioration, missed seepage paths |
| Upstream face (incl. underwater) | Cracks, damaged waterstops, deposits | Increased leakage |
| Fill dam slopes & crest | Settlement, cracks, displaced riprap, wet areas downstream | Missed seepage change leading to internal erosion |
| Inspection galleries | Changing leakage, deposits, clogged drains | Rising uplift pressure, reduced stability |
| Spillway & stilling basin | Abrasion and cavitation damage, slab uplift, scour | Failure during release |
| Gates & hoists | Corrosion, coating loss, worn seals, deformation | Gates that will not open or close when needed |
| Reservoir & rim slopes | Sedimentation, slope failure and landslides, driftwood | Lost capacity, blocked outlets |
Today’s inspection and its pain points
In Japan, dam operators carry out daily patrols and instrument monitoring under the River Act, and dams also receive periodic government inspections. Since 2013, dams that are river management facilities also undergo a “comprehensive dam inspection” within 30 years of entering service and roughly every 30 years after, assessing long-term ageing and the condition of the dam body. Hydropower dams are additionally covered by electricity-sector inspection rules.
The pain is height, water and tight spaces. Tall downstream faces are inspected by rope access or from gondolas. Below the waterline on the upstream face, divers or ROVs are needed, and deep cold water is dangerous for people. Galleries are dark and damp, and the inside of gates and outlet conduits is cramped. Windows when the reservoir can be drawn down for inspection are limited.
| Method | Strength | Pain point |
|---|---|---|
| Daily patrols & instruments | Track leakage, movement and uplift daily | Cannot tell *why* something changed |
| Rope access & gondolas (downstream face) | Close visual and sounding | Fall risk, few experts, takes days |
| Divers (upstream face, intakes) | Direct view underwater | Depth, cold and poor visibility; short bottom times |
| ROVs | Reach depth safely | Turbidity blinds cameras; hard to know position |
| Scaffolding (gates & outlets) | Reliable close access | Time and cost; tied to drawdown windows |
What drones change
At dams the rule is to combine aerial and underwater drones. Aircraft take the downstream face and the exposed upstream face; caged aircraft take galleries, outlet conduits and penstocks; underwater ROVs and uncrewed surface vessels take what lies below the waterline.
| Approach | Typical aircraft & sensors | Best for |
|---|---|---|
| Photogrammetry & 3D of the body | RTK GNSS drone with high-resolution camera | Downstream face, crest, exposed upstream face; crack maps and change |
| Close-range imaging | Drones with zoom cameras, autonomous aircraft (e.g. Skydio X10 class) | Joints, leak stains, spillway walls and slabs |
| Collision-tolerant interior inspection | Caged drone with lighting (e.g. Flyability Elios 3) | Galleries, outlet conduits, penstocks, gate chambers |
| Underwater inspection | ROVs and sonar | Submerged upstream face, intakes, clogged trash racks |
| Reservoir survey | Uncrewed boat with echo sounder, drone LiDAR | Sediment volumes, rim-slope change |
| Thermal imaging | Drones with thermal cameras | Candidate seepage on fill dam downstream faces (condition-dependent) |
The downstream face is flown as a grid at constant stand-off. Walls over a hundred metres are split into vertical bands, divided at the joints, which makes mapping onto drawings easier. When the reservoir is drawn down, parts of the upstream face normally under water can be photographed from the air — don’t miss that chance.
Overcoming the environment
A dam gathers almost every condition drones find hard. Deep valleys narrow the sky and degrade GNSS; valley winds are strong and shifting. The foot of the downstream face has spray from releases, galleries are pitch dark and humid, and conduits and penstocks are confined.
- GNSS-denied: GNSS fails at the toe and in galleries. Use aircraft that localise from LiDAR or cameras, and check satellite reception at the valley floor in advance. GNSS-denied
- Height: the dam’s height strains sight lines and links. Consider crew both on the crest and downstream. Height
- Wind & turbulence: winds funnel through the valley and roll off the dam face. Keep an escape route away from the wall. Wind & turbulence
- Water & humidity: spray and humidity fog lenses and wet aircraft; watch for condensation in galleries. Avoid flying during releases. Water, spray & humidity
- Darkness: galleries and penstocks rely on onboard lighting. Lock exposure and repeat last time’s conditions. Darkness
- Confined spaces: conduits, penstocks and gate chambers have close walls. Use caged aircraft and battery plans with turn-back margin. Confined spaces
From images to decisions
Dam inspection data comes alive when images, point clouds and instrument records are overlaid on one model of the dam. Divide crack maps by joint number and check whether zones of rising leakage coincide with growing cracks. AI is good at proposing cracks, leak stains and deposits and at showing change. Evaluating dam safety is the responsibility of dam engineers and specialists.
| Step | What machines do | What people own |
|---|---|---|
| Modelling | Build 3D models and orthomosaics of the dam from images and LiDAR | Control points, accuracy, match to joint numbers |
| Detection & measurement | Propose and size cracks, leak stains, spalls, deposits | Check misses and false alarms |
| Change over time | Differences from the last model and images | Interpret what the progression means |
| Link to instruments | Overlay leakage, movement and uplift records by location | Infer causes and decide on further investigation |
| Assessment & action | — | Safety evaluation, repair plans, operating decisions (water level, releases) |
A dam is built to serve for a century. The images taken today will be the baseline for engineers fifty years from now. Store joint number, camera pose, capture conditions and reservoir level with every image — the cheapest and most effective investment there is.
For a template that turns images and AI findings into a report the owner can act on, see writing up drone and AI findings as an inspection report (Airffic Flight Institute).
Rules and responsibility
In Japan, dams are managed under the River Act and its rules on structure and operation, with electricity-sector rules also applying to hydropower dams. There are few nationwide rules specifically governing drone use in dam inspection, so which records are used and how is up to the operator and the inspecting authority. Dams are mostly in mountains outside densely inhabited districts, but flights close to the dam and its equipment, or beyond visual line of sight, must be checked against the specified-flight rules.
Abroad, the US Federal Energy Regulatory Commission (FERC) requires independent consultants to inspect certain licensed hydropower dams (for example, those over 10 m high) every five years, with a comprehensive assessment every ten. In England and Wales the Reservoirs Act 1975 requires inspection and supervision by qualified engineers for high-risk large reservoirs (now those holding 10,000 m³ or more). The International Commission on Large Dams (ICOLD) publishes technical guidance on dam safety. Compare countries in world regulations.
What drones cannot do
- Inside the body and the foundation: internal cracks, foundation rock and seepage paths do not appear in photos. They belong to instruments, boreholes and geophysics.
- Sounding & touch: tapping concrete for delamination is still done by people up close.
- Turbid water: underwater drones see nothing in heavy turbidity; combine with sonar and divers.
- Gate operation tests: actually opening and closing gates and checking hoists is mechanical inspection work.
- Safety evaluation and operating decisions: water level and releases are decided by operators and specialists.
2035: the world where inspection works
In the Airffic editors’ view, it goes like this. A drone port sits on the roof of the dam control office and photographs the downstream face along the same route each season. A caged aircraft waits in the gallery and, on any day the leakage readings change, flies that section and records it. Once a year an underwater drone dives, adding the upstream face and intakes to the same dam model.
Instead of hanging from ropes, engineers trace a century of change on the model. Dives and descents down the wall become rare. Dam inspection turns from a job of going to dangerous places into a job of carrying a hundred-year record forward.
PREPARATION
Pre-flight preparation checklist
Ticks are saved on this device (and to your shared account if signed in). This is a learning aid, not proof of permission or safety.
Cases for this asset
- VZU Plzeň: caged-drone inspection of a 700 m hydropower penstockCzech Republic · 2024
- TEPCO Renewable Power: remote post-earthquake drone inspection trial at Kazunogawa DamOtsuki, Yamanashi, Japan · 2024
Related papers
Country sources(62)
- Guidebook for Promoting Drone Use and Development in the Construction SectorJP · 国土交通省(大臣官房技術調査課系)
- Japan's first Level 3.5 drone flight for dam maintenanceJP · 国土交通省 中部地方整備局 長島ダム管理所
- Demonstration of remote-operated drone emergency inspection of a damJP · 東京電力リニューアブルパワー
- Drone demonstration at Yokose River DamJP · 国土交通省 四国地方整備局 渡川ダム統合管理事務所
- Ministry of Environment and K-water: drones and AI to handle dam safetyKR · 뉴스토마토
- Nuclear safety: from intelligent CCTV to drones and robotsKR · 에너지경제신문
- Geumho River and Sincheon: stronger facility safety with dronesKR · 경북매일
- Drone, robot dog and radar: ministry experts inspect a Chengdu reservoirCN · 川观新闻(四川日报)
- Industrial inspections cost companies millions, these Indian drones and ROVs startups can change thatIN · The News Minute
- How this Chennai-based startup is pioneering underwater AI-based ROVsIN · INDIAai (Government of India AI portal)
- Diving into deep tech: How Indian startups are securing the underwater foundations of tradeIN · The Week
- Underwater roverIN · Outlook Business
Check the evidence
Rules, figures and cases cite the sources below. Future scenarios and design proposals are the editors’ own view.
- MLIT: Guidelines for comprehensive dam inspection (1 October 2013)MLIT Water and Disaster Management Bureau · Full text read
- eCFR: 18 CFR Part 12 — Safety of Water Power Projects and Project WorksU.S. Government Publishing Office / FERC · Full text read
- Reservoirs Act 1975legislation.gov.uk (The National Archives) · Abstract read
- International Commission on Large Dams (ICOLD): BulletinsICOLD · Full text read
- MLIT: Permission and approval procedures for unmanned aircraft (specified flights)MLIT Civil Aviation Bureau · Full text read
Sources checked: 2026-10-22